SGIP for >30 kW with battery-based storage is a three-step process for the installer. This document outlines the major steps. Please refer to the SGIP Handbook for in depth descriptions of the items involved
Once the installer has completed these items, assuming ETB was listed as the PDP, ETB will begin the PDP process for the site. ETB is to:
Provide the installer with 7-day discharge data and full capacity discharge data for the performance based portion of the incentive application
The installer is responsible for submitting this required data to SGIP
When notified by SGIP, ETB will begin the monthly submission of meter and app files
To do this ETB will require from the installer:
SGIP application ID
Conditional Reservation Letter date
The date of expected start of monthly data reporting
Please Note: It is the responsibility of the installer to complete the application process and alert ETB of all deadlines and any modifications to the applications.